EARNED VALUE & VARIANCE ANALYSIS |
|
Earned Value Management (EVM) Metrics: CPI, SPI,
CV, SV, EAC, ETC |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
WBS Phase |
BAC ($) |
Planned Value ($) |
Earned Value ($) |
Actual Cost ($) |
% Complete |
% Planned |
CV ($) |
SV ($) |
CPI |
SPI |
EAC ($) |
ETC ($) |
TCPI |
|
1.1 Pre-Construction |
$720,000 |
$720,000 |
$684,000 |
$620,000 |
95.0% |
100.0% |
$64,000 |
-$36,000 |
1.10 |
0.95 |
$652,632 |
$32,632 |
0.36 |
|
1.2 Site Work |
$1,125,000 |
$787,500 |
$731,250 |
$980,000 |
65.0% |
70.0% |
-$248,750 |
-$56,250 |
0.75 |
0.93 |
$1,507,692 |
$527,692 |
2.72 |
|
1.3 Foundations & Structure |
$2,820,000 |
$1,410,000 |
$1,269,000 |
$2,350,000 |
45.0% |
50.0% |
-$1,081,000 |
-$141,000 |
0.54 |
0.90 |
$5,222,222 |
$2,872,222 |
3.30 |
|
1.4 Building Envelope |
$1,625,000 |
$406,250 |
$325,000 |
$850,000 |
20.0% |
25.0% |
-$525,000 |
-$81,250 |
0.38 |
0.80 |
$4,250,000 |
$3,400,000 |
1.68 |
|
1.5 MEP Systems |
$3,785,000 |
$757,000 |
$567,750 |
$1,500,000 |
15.0% |
20.0% |
-$932,250 |
-$189,250 |
0.38 |
0.75 |
$10,000,000 |
$8,500,000 |
1.41 |
|
1.6 Interior Finishes |
$1,130,000 |
$113,000 |
$56,500 |
$420,000 |
5.0% |
10.0% |
-$363,500 |
-$56,500 |
0.13 |
0.50 |
$8,400,000 |
$7,980,000 |
1.51 |
|
1.7 Specialties & Equipment |
$1,245,000 |
$62,250 |
$24,900 |
$180,000 |
2.0% |
5.0% |
-$155,100 |
-$37,350 |
0.14 |
0.40 |
$9,000,000 |
$8,820,000 |
1.15 |
|
1.8 PM & Closeout |
$1,245,000 |
$498,000 |
$435,750 |
$750,000 |
35.0% |
40.0% |
-$314,250 |
-$62,250 |
0.58 |
0.88 |
$2,142,857 |
$1,392,857 |
1.63 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL PROJECT |
$13,695,000 |
$4,754,000 |
$4,094,150 |
$7,650,000 |
29.9% |
34.7% |
-$3,555,850 |
-$659,850 |
0.54 |
0.86 |
$25,589,378 |
$17,939,378 |
1.59 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
EVM METRIC INTERPRETATION GUIDE |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Metric |
Formula |
Favorable |
Unfavorable |
|
|
|
|
|
|
|
|
|
|
|
CV (Cost Variance) |
EV - AC |
CV > 0 (Under budget) |
CV < 0 (Over budget) |
|
|
|
|
|
|
|
|
|
|
|
SV (Schedule Variance) |
EV - PV |
SV > 0 (Ahead) |
SV < 0 (Behind) |
|
|
|
|
|
|
|
|
|
|
|
CPI (Cost Performance Index) |
EV / AC |
CPI > 1.0 |
CPI < 1.0 |
|
|
|
|
|
|
|
|
|
|
|
SPI (Schedule Perf Index) |
EV / PV |
SPI > 1.0 |
SPI < 1.0 |
|
|
|
|
|
|
|
|
|
|
|
EAC (Estimate at Completion) |
BAC / CPI |
EAC < BAC |
EAC > BAC |
|
|
|
|
|
|
|
|
|
|
|
ETC (Estimate to Complete) |
EAC - AC |
Remaining work cost |
|
|
|
|
|
|
|
|
|
|
|
TCPI (To-Complete Perf Index) |
(BAC-EV)/(BAC-AC) |
TCPI < 1.0 (Achievable) |
TCPI > 1.0 (Difficult) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
THRESHOLD INDICATORS |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Indicator |
Range |
Action Required |
|
|
|
|
|
|
|
|
|
|
|
|
GREEN |
CPI/SPI 0.95 - 1.05 |
On track, continue
monitoring |
|
|
|
|
|
|
|
|
|
|
|
YELLOW |
CPI/SPI 0.85 - 0.94 or 1.06 - 1.15 |
Caution, investigate root
cause |
|
|
|
|
|
|
|
|
|
|
|
RED |
CPI/SPI < 0.85 or > 1.15 |
Critical, corrective
action needed |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Note: Blue values (% Complete, % Planned) are
inputs. Green values reference other sheets. Update regularly for accurate
EVM tracking. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|