CONSTRUCTION PROJECT COST MANAGEMENT DASHBOARD
[Enter Project Name]
KEY PERFORMANCE INDICATORS
Total Project Budget Actual Cost to Date Cost Perf Index (CPI) Schedule Perf Index (SPI) % Complete (Earned)
$19,048,500 $7,650,000 0.54 0.86 29.9%
COST BY PHASE
Phase Budget ($) Actual ($) Variance ($) % Spent Status
1.1 Pre-Construction $720,000 $620,000 $100,000 86.1% OK
1.2 Site Work $1,125,000 $980,000 $145,000 87.1% OK
1.3 Foundations & Structure $2,820,000 $2,350,000 $470,000 83.3% OK
1.4 Building Envelope $1,625,000 $850,000 $775,000 52.3% OK
1.5 MEP Systems $3,785,000 $1,500,000 $2,285,000 39.6% OK
1.6 Interior Finishes $1,130,000 $420,000 $710,000 37.2% OK
1.7 Specialties & Equipment $1,245,000 $180,000 $1,065,000 14.5% OK
1.8 PM & Closeout $1,245,000 $750,000 $495,000 60.2% OK
TOTAL $13,695,000 $7,650,000 $6,045,000 55.9%  
CONTINGENCY & CHANGE ORDER STATUS
Contingency Budget: $1,867,500 Approved Change Orders: 0
Contingency Used: $160,000 Pending Change Orders: 0
Contingency Remaining: $1,707,500 CO Total Value: $0
QUICK NAVIGATION
▶ Project Setup Project details & assumptions
▶ WBS   Work breakdown structure            
▶ Cost Estimation   Detailed cost breakdown            
▶ Cost Baseline   Time-phased budget            
▶ Actual Costs   Expenditure tracking              
▶ Variance Analysis   EVM metrics & analysis            
▶ Change Orders   Change order log              
▶ Contingency Planning Risk register & contingency            
▶ Cash Flow   Cash flow projections            
▶ Resource Plan   Labor & equipment plan            
▶ Reports   Executive summary report            
Note: All values are dynamically linked to source sheets. Dashboard updates automatically when source data changes.