EXECUTIVE COST REPORT
Project Cost Status Summary for Management Review
PROJECT INFORMATION            
Project Name: [Enter Project Name]
Project ID: PROJ-2026-001
Report Date: 02/12/2026
Reporting Period: Q1 2026
Project Manager: [Enter Estimator Name]
Project Status: On Track
COST SUMMARY              
Original Budget (BAC): $19,048,500
Approved Change Orders: $0          
Revised Budget: $19,048,500          
Actual Cost to Date: $7,650,000          
Committed Costs: $10,950,000          
Forecast at Completion: $14,860,000          
Variance (Budget vs Forecast): $4,188,500          
Contingency Remaining: $1,707,500          
EARNED VALUE METRICS            
Cost Performance Index (CPI): 0.54
Schedule Performance Index (SPI): 0.86          
Cost Variance ($): -$3,555,850          
Schedule Variance ($): -$659,850          
Estimate at Completion (EAC): $25,589,378          
Estimate to Complete (ETC): $17,939,378          
% Budget Spent: 55.9%          
% Project Complete (Earned): 29.9%          
KEY ISSUES & ACTIONS            
Item Issue / Risk Impact Action Required Owner Due Date Status  
1 Steel delivery delayed 2 weeks Medium Expedite with supplier Procurement 3/15/2026 Open
2 Subcontractor pricing higher than estimate High Negotiate or rebid PM 3/20/2026 Open  
3 Weather delays in Q3 Low Monitor forecast, adjust schedule Scheduler Ongoing Monitoring  
  [Enter issue]            
  [Enter issue]            
Note: This report pulls data from all model sheets. Green values are cross-sheet references. Update Actual Costs and Variance Analysis for current data.