| CHANGE ORDER MANAGEMENT | |||||||||||
| Change Order Log with Cost & Schedule Impact Tracking | |||||||||||
| Total Change Orders: | 2 | Total Approved Cost: | $0 | ||||||||
| Approved COs: | 0 | Total Pending Cost: | $0 | ||||||||
| Pending COs: | 0 | % of Original Budget: | 0.0% | ||||||||
| Rejected COs: | 0 | ||||||||||
| CO # | Date | Description | WBS Code | Cost Impact ($) | Schedule Impact (Days) | Status | Requested By | Approved By | Approval Date | Notes | |
| CO-001 | 4/15/2026 | Additional foundation piles - soil conditions | 1.3.1 | 125000 | $14 | Approved | Geotech Eng | PM | 4/20/2026 | Unforeseen soil | |
| CO-002 | 5/10/2026 | Owner requested upgraded HVAC system | 1.5.1 | 285000 | $7 | Approved | Owner | PM | 5/18/2026 | Owner directive | |
| CO-003 | 6/1/2026 | Design revision - lobby area expansion | 1.6.1 | 95000 | $10 | Approved | Architect | PM | 6/8/2026 | Design change | |
| CO-004 | 7/15/2026 | Additional fire protection in parking | 1.5.3 | 75000 | $5 | Pending | Fire Marshal | Code compliance | |||
| CO-005 | 8/1/2026 | Value engineering - alternate cladding | 1.4.2 | -45000 | - | Pending | PM | Cost saving | |||
| CO-006 | 8/15/2026 | Additional electrical outlets per floor | 1.5.2 | 35000 | $3 | Rejected | Tenant | PM | 8/20/2026 | Not in scope | |
| [Enter description] | |||||||||||
| [Enter description] | |||||||||||
| [Enter description] | |||||||||||
| [Enter description] | |||||||||||
| Note: Blue values are sample data. Log all change orders with cost and schedule impacts for accurate project tracking. | |||||||||||