CHANGE ORDER MANAGEMENT
Change Order Log with Cost & Schedule Impact Tracking
Total Change Orders: 2     Total Approved Cost: $0      
Approved COs: 0     Total Pending Cost:   $0      
Pending COs: 0     % of Original Budget: 0.0%      
Rejected COs: 0                
CO # Date Description WBS Code Cost Impact ($) Schedule Impact (Days) Status Requested By Approved By Approval Date Notes
CO-001 4/15/2026 Additional foundation piles - soil conditions 1.3.1 125000 $14 Approved Geotech Eng PM 4/20/2026 Unforeseen soil
CO-002 5/10/2026 Owner requested upgraded HVAC system 1.5.1 285000 $7 Approved Owner PM 5/18/2026 Owner directive
CO-003 6/1/2026 Design revision - lobby area expansion 1.6.1 95000 $10 Approved Architect PM 6/8/2026 Design change
CO-004 7/15/2026 Additional fire protection in parking 1.5.3 75000 $5 Pending Fire Marshal     Code compliance
CO-005 8/1/2026 Value engineering - alternate cladding 1.4.2 -45000 - Pending PM     Cost saving
CO-006 8/15/2026 Additional electrical outlets per floor 1.5.2 35000 $3 Rejected Tenant PM 8/20/2026 Not in scope
    [Enter description]                
    [Enter description]                
    [Enter description]                
    [Enter description]                
Note: Blue values are sample data. Log all change orders with cost and schedule impacts for accurate project tracking.