CONTINGENCY & RISK MANAGEMENT |
|
Risk Register, Contingency Budget Tracking &
Drawdown Log |
|
|
|
|
|
|
|
|
|
|
|
CONTINGENCY BUDGET
SUMMARY |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Original Contingency
Budget: |
|
$1,245,000 |
|
|
|
|
|
|
Management Reserve: |
|
$622,500 |
|
|
|
|
|
|
Total Risk Budget: |
|
|
$1,867,500 |
|
|
|
|
|
|
Contingency Used: |
|
$160,000 |
|
|
|
|
|
|
Contingency Remaining: |
|
$1,707,500 |
|
|
|
|
|
|
% Remaining: |
|
|
91.4% |
|
|
|
|
|
|
Contingency Rate
Applied: |
|
10.0% |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
RISK REGISTER |
|
|
|
|
|
|
|
|
|
|
|
Risk ID |
Risk Description |
Category |
Probability |
Impact ($) |
Risk Score ($) |
Mitigation Strategy |
Owner |
Status |
|
R-001 |
Unforeseen subsurface conditions |
Geotechnical |
40% |
$350,000 |
$140,000 |
Additional soil testing |
Geotech Eng |
Active |
|
R-002 |
Material price escalation (steel) |
Market |
60% |
$200,000 |
$120,000 |
Early procurement, fixed-price contracts |
Procurement |
Active |
|
R-003 |
Skilled labor shortage |
Resource |
50% |
$180,000 |
$90,000 |
Pre-qualify subcontractors |
PM |
Active |
|
R-004 |
Weather delays (winter season) |
Weather |
30% |
$150,000 |
$45,000 |
Schedule float, weather days |
Scheduler |
Active |
|
R-005 |
Design changes by owner |
Scope |
50% |
$250,000 |
$125,000 |
Design freeze agreement |
PM |
Active |
|
R-006 |
Permit delays |
Regulatory |
25% |
$100,000 |
$25,000 |
Early engagement with authorities |
PM |
Mitigated |
|
R-007 |
Equipment failure / breakdown |
Equipment |
20% |
$80,000 |
$16,000 |
Maintenance schedule, backup equipment |
Site Supt |
Active |
|
R-008 |
Subcontractor default |
Subcontract |
15% |
$400,000 |
$60,000 |
Performance bonds, backup subs |
PM |
Active |
|
R-009 |
Environmental contamination found |
Environmental |
10% |
$500,000 |
$50,000 |
Environmental assessment |
Env Mgr |
Active |
|
R-010 |
Code/regulation changes |
Regulatory |
15% |
$120,000 |
$18,000 |
Monitor regulatory updates |
PM |
Active |
|
Total Risk Exposure: |
|
|
|
$689,000 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
CONTINGENCY DRAWDOWN LOG |
|
|
|
|
|
|
|
|
|
|
|
Date |
Description |
Risk ID |
WBS Code |
Amount ($) |
Cumulative ($) |
Approved By |
Justification |
|
|
5/1/2026 |
Additional piling - soft soil |
R-001 |
1.3.1 |
$85,000 |
$85,000 |
PM |
Unforeseen ground
conditions |
|
6/15/2026 |
Steel price increase |
R-002 |
1.3.3 |
$45,000 |
$130,000 |
PM |
Market escalation |
|
7/20/2026 |
Weather delay mitigation |
R-004 |
1.2.2 |
$30,000 |
$160,000 |
PM |
Acceleration costs |
|
|
[Enter description] |
|
|
|
$160,000 |
|
|
|
|
|
[Enter description] |
|
|
|
$160,000 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Note: Risk register uses sample data. Update
probability, impact, and mitigation strategies based on actual project risks. |
|
|
|
|
|
|
|
|
|
|