| RESOURCE ALLOCATION PLAN | |||||||||||
| Labor FTE Allocation & Equipment Plan by Quarter | |||||||||||
| LABOR RESOURCE ALLOCATION (FTE) | |||||||||||
| Resource Type | Rate ($/hr) | Q1 2026 | Q2 2026 | Q3 2026 | Q4 2026 | Q1 2027 | Q2 2027 | Q3 2027 | Q4 2027 | Q1 2028 | |
| Project Manager | $95 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | |
| Site Superintendent | $85 | 0.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 0.5 | |
| Civil Engineers | $75 | 2.0 | 3.0 | 4.0 | 2.0 | 1.0 | 0.0 | 0.0 | 0.0 | 0.0 | |
| Structural Engineers | $80 | 0.0 | 1.0 | 2.0 | 3.0 | 3.0 | 2.0 | 1.0 | 0.0 | 0.0 | |
| MEP Engineers | $78 | 0.0 | 0.0 | 0.0 | 1.0 | 2.0 | 3.0 | 3.0 | 2.0 | 1.0 | |
| Safety Officers | $65 | 0.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 1.0 | 0.5 | |
| QC Inspectors | $60 | 0.0 | 0.0 | 1.0 | 1.0 | 2.0 | 2.0 | 2.0 | 1.0 | 1.0 | |
| Surveyors | $55 | 2.0 | 2.0 | 1.0 | 0.5 | 0.0 | 0.0 | 0.0 | 0.0 | 0.0 | |
| General Laborers | $35 | 0.0 | 5.0 | 10.0 | 15.0 | 20.0 | 18.0 | 15.0 | 8.0 | 3.0 | |
| Skilled Trades (Electrical) | $55 | 0.0 | 0.0 | 0.0 | 2.0 | 4.0 | 6.0 | 6.0 | 4.0 | 2.0 | |
| Skilled Trades (Plumbing) | $52 | 0.0 | 0.0 | 0.0 | 2.0 | 3.0 | 4.0 | 4.0 | 3.0 | 1.0 | |
| Skilled Trades (HVAC) | $58 | 0.0 | 0.0 | 0.0 | 1.0 | 3.0 | 5.0 | 5.0 | 3.0 | 1.0 | |
| Carpenters / Framers | $48 | 0.0 | 0.0 | 3.0 | 5.0 | 6.0 | 8.0 | 8.0 | 5.0 | 2.0 | |
| Iron Workers | $50 | 0.0 | 0.0 | 2.0 | 6.0 | 8.0 | 4.0 | 2.0 | 0.0 | 0.0 | |
| TOTAL FTE | 5.0 | 14.0 | 26.0 | 41.5 | 55.0 | 55.0 | 49.0 | 29.0 | 13.0 | ||
| QUARTERLY LABOR COST | $184,600 | $434,200 | $735,280 | $1,111,500 | $1,442,480 | $1,456,520 | $1,308,320 | $796,120 | $379,080 | ||
| EQUIPMENT ALLOCATION | |||||||||||
| Equipment Type | Monthly Rate ($) | Q1 2026 | Q2 2026 | Q3 2026 | Q4 2026 | Q1 2027 | Q2 2027 | Q3 2027 | Q4 2027 | Q1 2028 | |
| Excavators (CAT 320) | $15,000 | 0 | 2 | 3 | 1 | 0 | 0 | 0 | 0 | 0 | |
| Bulldozers (D6) | $12,000 | 0 | 1 | 2 | 1 | 0 | 0 | 0 | 0 | 0 | |
| Cranes (Tower) | $25,000 | 0 | 0 | 1 | 1 | 2 | 2 | 1 | 0 | 0 | |
| Cranes (Mobile) | $18,000 | 0 | 0 | 0 | 1 | 2 | 1 | 1 | 0 | 0 | |
| Concrete Pumps | $8,000 | 0 | 0 | 1 | 2 | 1 | 0 | 0 | 0 | 0 | |
| Generators | $3,500 | 0 | 1 | 2 | 2 | 2 | 2 | 1 | 1 | 0 | |
| Scaffolding Sets | $5,000 | 0 | 0 | 0 | 5 | 8 | 10 | 10 | 6 | 2 | |
| Forklifts / Telehandlers | $6,000 | 0 | 0 | 1 | 2 | 2 | 2 | 2 | 1 | 0 | |
| QUARTERLY EQUIP COST | $0 | $136,500 | $345,000 | $390,000 | $459,000 | $411,000 | $325,500 | $118,500 | $30,000 | ||
| Note: FTE counts and equipment allocations are sample data. Blue values are editable inputs. Adjust based on actual project staffing plan. | |||||||||||